Plant breakdowns have plunged South Africa back into stage-6 load shedding. The struggling state-owned utility announced it will impose the severe cuts, up from stage 5, from 4pm on Wednesday.

Blaming a shortage of generation capacity, the utility said stage 5 will be implemented from 5am to 4pm on Thursday, with a return to stage 6 thereafter. “This pattern will be repeated daily until further notice,” it said.

Breakdowns have reached 16.8GW of capacity, while plant out on planned maintenance was at 5.8GW of capacity.

Read: ‘It’s hell’: Mobile networks face load shedding nightmare

Over the past 24 hours, two Eskom generation units were returned to service at Kriel power station. However, outages elsewhere have exacerbated the situation:

  • A generating unit at Duvha power station was taken offline for repairs.
  • Delays in returning a unit each to service at Camden, Kendal, Lethabo, Medupi and Tutuka power stations have contributed to the capacity constraints.
  • Similarly, the increase in demand after the long weekend and the re-opening of schools has put additional strain on the power generation system.

Eskom did not provide an outlook for the weekend.  – © 2023 NewsCentral Media

Get TechCentral’s daily newsletter

Source

BADEA: the Arab Bank for Economic Development at work in Senegal

Previous article

Peru’s ex-president fails to stave off extradition

Next article

You may also like

Comments

Comments are closed.

More in Techno